Bellmer plant # 3 starts to take shape
As reported in Info 78, our new 5,000 square-meter facility, plant # 3, gives us more space and therefore more efficient assembly of large paper machine parts up to 8 m in width. This is also where our modernised roll production will be located. The ground-breaking ceremony took place on 5th March this year, since then there has been tremendous progress. Concrete construction works were completed in early May, the hall crane tracks have been mounted, and the fitting out of the interior is underway.

We are on schedule to complete construction works by late October, with the move into the new buildings slated for the end of 2012.
The future assembly hall for Paper Technology